Find
20 Jan 2025

Eurex Clearing

Eurex Clearing Readiness Newsflash | Frozen Zones for Simulation and Production launch in 2025

Eurex Clearing Readiness Newsflash | Frozen Zones for Simulation and Production launch in 2025

Dear customer,

With this Newsflash, Eurex Clearing announces the scheduled frozen zones in preparation for the Simulation and Production launches of the Eurex Clearing Releases in 2025.

An up-to-date timetable can be found on our dedicated Initiatives page in the following location:

Support > Initiatives & Releases

The frozen zones are mandatory to ensure a smooth introduction of new software on a stable data basis.

Simulation: 

Frozen Zone

Release

Simulation Launch

25.03.2025 - 01.04.2025

Prisma 14.1

01.04.2025

03.04.2025 - 10.04.2025

EurexOTC Clear 19.0

09.04.2025

10.04.2025 - 15.04.2025

C7 SCS 4.5

14.04.2025

26.08.2025 - 02.09.2025

Prisma 15.0

02.09.2025

11.09.2025 - 16.09.2025

C7 SCS 5.0

15.09.2025

25.09.2025 - 02.10.2025

EurexOTC Clear 20.0

01.10.2025

Production: 

Frozen Zone

Release

Simulation Launch

20.03.2025 - 25.03.2025

CBPR+ Wave 4*

21.03.2025

15.05.2025 - 20.05-2025

T7 13.1, EurexOTC Clear 19.0, Prisma 14.1

19.05.2025

12.06.2025 - 16.06.2025 

C7 SCS 4.5

16.06.2025

12.06.2025 - 17.06.2025

CBPR+ wave 5*

13.06.2025

18.09.2025 - 23.09.2025

CBPR+ wave 6*

19.09.2025

06.11.2025 - 11.11.2025

T7 14.0, EurexOTC Clear 20.0, Prisma 15.0 

10.11.2025

13.11.2025 - 18.11.2025

CBPR+ wave 7*

14.11.2025

20.11.2025 - 25.11.2025

C7 SCS 5.0 

24.11.2025

* For Eurex Clearing, no new member setup and member reference data modifications to be considered. Exceptions to be considered case to case, depending on system impact.
 

Important Information on Onboarding Activities and Restrictions

General Restrictions:

During the above-mentioned time periods, unless otherwise stated, it is prohibited to execute any processes in the simulation or production environments that involve changes to reference data for Clearing Members and clients. 


This includes account changes, product maintenance, Clearer changes, Member or user changes, cancellation of membership, new membership, and static data updates. Please note that the timelines provided are indicative, and Clearing Members are strongly encouraged to factor in these timelines, particularly for client onboarding activities.
 

EurexOTC Clear and PRISMA Releases: Impact on OTC IRS Onboarding Activities:

EurexOTC Clear and PRISMA Releases will impact the processing of OTC IRD-related onboarding requests (only applicable for production) and must be considered when planning new onboardings. 

During the Frozen Zone, the following onboarding activities for OTC IRS will not be supported:

  • New Disclosed Client with Member ID
  • New Fund Manager (FM) with Member ID
  • New Fund(s) under an existing FM
  • New DC in A-Account of the Clearing Member
  • New FCM Client

Frozen Zones with No Impact on OTC IRD Onboarding:

Frozen Zones related to the C7 SCS Releases do not affect OTC IRD-related onboarding requests.

CBPR + Considerations:

The impact of CBPR+ varies on a case-by-case basis (e.g., in the case of new cash accounts).

Recommendations:

  • Clearing Members are advised to apply for any changes or new setups well in advance of the Frozen Zone or wait until the period concludes.
  • Buy-side client onboardings can still be initiated at any time using the Client Onboarding Tool (C7 CAS). The Onboarding team will confirm the go-live date for such requests.

If you have questions or comments, please send an e-mail to client.services@eurex.com.

Kind regards,
Your Client Services Team

 

Visit now Eurex Support Clearing to access a wide array of support content!


Further information

Recipients: 

All Clearing Members, ISA Direct Clearing Members, Disclosed Direct Clients of Eurex Clearing AG and vendors

Target groups: 

Front Office/Trading, Middle + Backoffice, IT/System Administration, Auditing/Security Coordination 

Contact: 

client.services@eurex.com 

Web: 

Support > Initiatives & Releases